5.0          RATE-LTP                                                                     Back

            

    This tariff shall be applicable for motive power services

 

L1(LTP-I)- INDUSTRIAL  Conn. Up to 125 BHP

 

5.1              RATE LTP-I

 

5.1.1.    Fixed charges per month:

 

For an installation having the contracted load upto 10 BHP

Rs.22/- per BHP

For installation having contracted load exceeding 10 BHP:

(i) For first 10 BHP of contracted load

Rs.22/- per BHP

(ii) For next 40 BHP of contracted load

Rs.40/- per BHP

(iii) For next 25 BHP of contracted load

Rs.65/- per BHP

(iv) For next 25 BHP of contracted load

Rs.100/- per BHP

(v) Balance BHP of contracted load

Rs.155/- per BHP

 

PLUS

5.1.2   Energy charges:

 

 

(a)

For installation having contracted load upto and including 10 BHP:

For entire consumption during the month

350 Paise per Unit

 

(b)

For installation having contracted load exceeding 10 BHP:

For entire consumption during the month

375 Paise per Unit

 

PLUS

5.1.3 Reactive Energy Charges:

 

For installation having contracted load of 50 BHP and above for all reactive units (KVRAH) drawn during the month

10 Paise per KVARH

 

5.1.4 Minimum bill per installation per month for consumers other than Seasonal Consumers:

 

(a)

When contracted load is upto 75 BHP

Rs.105 per BHP

(b)

When contracted load exceeds 75 BHP

Rs.180 per BHP

 

5.1.5 Minimum Bill Per Installation for Seasonal Consumers

 

(a)             “Seasonal Consumer”, shall mean a consumer who takes and uses power supply for ice factory, ice candy machines, ginning and pressing factory, oil mill, rice mill, huller, salt industry, sugar factory, khandsari, cold storage plants (including such plants in fisheries industry), tapioca industries manufacturing starch, etc.

(b)             Any consumer, who desires to be billed for the minimum charges on annual basis shall intimate to that effect in writing in advance about the off-season period during which energy consumption, if any, shall be mainly for overhauling of the plant and machinery.  The total period of the off-season so declared and observed shall be not less than three calendar months in a calendar year.

(c)             The total minimum amount under the head “Fixed and Energy Charges” payable by the seasonal consumer satisfying the eligibility criteria under sub-clause (a) above and complying with the provision stipulated under sub-clause (b) above shall be Rs.1200/- per annum per BHP of the contracted load for the installation having the contracted load upto 75 BHP, and Rs.2000/- per annum per BHP when contracted load is exceeding 75 BHP.

(d)             The units consumed during the off-season period shall be charged for at a flat rate of 400 Paise per unit.

The electricity bills related to the off-season period shall not be taken into account towards the amount payable against the annual minimum bill. The amount paid by the consumer towards the electricity bills related to the seasonal period only under the heads “Fixed Charges” and “Energy Charges”, shall be taken into account while determining the amount of short-fall payable towards the annual minimum bill as specified under sub-clause (c) above.

L2-(LTP-II)

5.2             RATE LTP-II

 

This tariff shall be applicable to educational institutions and research and development laboratories for motive power services where machines and appliances are primarily used for demonstration/research purposes only.

 

5.2.1           Energy Charges

 

For all units consumed during the month

400 Paise per Unit

 

NOTE

The educational institutions and research laboratories will have an option to either select of the rate LTP-I with minimum charges or rate LTP-II without minimum charges.  The option can be exercised to switch over from LTP-I tariff to LTP-II and vice versa twice in a calendar year by giving not less than one month’s notice in writing.

 

L3-(LTP-III)

 

5.3             RATE LTP-III

 

This tariff shall be applicable to consumers using electricity for motive power services for minimum contract demand of 20 kW and up to 100 kW at low voltage.

5.3.1 Fixed charges:

 

(a)

For billing demand upto the contract demand

 

 

(i)      For first 20 to 40 kW of billing demand

Rs.65/- per kW per month

(ii)      Next 20 kW of billing demand

Rs.100/- per kW per month

(iii)     Above 60 kW of billing demand

Rs.165/- per kW per month

(b)

For billing demand in excess of the contract demand

Rs.210/- per kW

 

PLUS

5.3.2 Energy charges:

 

For the entire consumption during the month

395 Paise per Unit

 

                                                                                      PLUS

5.3.3 Reactive Energy Charges:

 

For all the reactive units (KVARH) drawn during the month

10 Paise per KVARH

         

5.3.4 Billing Demand

 

The billing demand shall be highest of the following, rounded to the next full kW:

(a)             Eighty-five percent of the contract demand

(b)             Actual maximum demand registered during the month

(c)             20 kW

 

5.3.5 Minimum Bill

 

Payment of demand charges every month based on the billing demand.

NOTE:

  1. This tariff shall be applicable if the consumer so opts to be charged in place of LTP-I Tariff.

  2. The option can be exercised to switch over from LTP-I tariff to LTP-III tariff and vice versa twice in a calendar year by giving not less than one month’s notice in writing.

  3. Consumer has to provide metering system in the event when proper metering system is not provided by Distribution Licensee.

  4. In the event of actual maximum demand exceeds 100 kW more than three occasions during the period of six months, the consumer has to provide his distribution transformer at his cost and maintain at his cost.

                                                                                                                                             Back