For using electricity exclusively during night hours. Back
15.0 RATE HTP-IV:
This tariff shall be applicable for supply of electricity to HT consumers contracted for 100 kVA and above for regular power supply and requiring the power supply for the purposes not specified in Rate HTP-II(A) and HTP-II(B); and consumer opting to use electricity exclusively during night hours from 10.00 PM to 06.00 AM next day.
15.1 Demand Charges:
|
Thirty percent of the demand charges specified in Rate HTP-I |
PLUS
15.2 Energy Charges:
|
For all units consumed during the month |
225 Paise per Unit |
15.3
Billing demand
15.4 Minimum bill
15.5 Power factor
15.6 Meter charges As per
15.7 Electricity duty and tax on sale of Electricity Rate
15.8 Maximum demand and its measurement HTP-I
15.9 Contract demand
15.10 Rebate for supply at EHV
15.11 Delayed payment charges
NOTE:
(i) 5% of total units consumed and 10% of the contract demand can be availed beyond the prescribed hours for the purpose of maintenance.
(ii) For the purpose of office lighting, fans etc. the consumer may apply for a separate connection.
(iii) This tariff shall be applicable if the consumer so opts to be charged in place of HTP-I tariff by using electricity exclusively during night hours as above.
(iv) The option can be exercised to switch over from HTP-I tariff to HTP-IV tariff and vice versa twice in a calendar year by giving not less than one month’s notice in writing.
(v) In case the consumer is not fulfilling the conditions of this tariff category, then such consumer for the relevant billing period will be billed under tariff category HTP-I.